How can PERT help us?
So what is PERT?
- Most likely (M) - The cost/duration of the activity, based on a realistic effort assessment for the required work and any predicted expenses.
- Optimistic(O) - The activity cost/duration based on an analysis of the best-case scenario for the activity.
- Pessimistic(P) - The activity cost/duration based on an analysis of the worst-case scenario for the activity.
How can PERT help us at activity level?
- 68% of the data will be found in one standard deviation from the mean in other words between the mean minus one standard deviation and the mean plus one standard deviation. We can also say that there is a 68% probability that the activity will be completed within one standard deviation from the mean.
- We also see that 95% of the data will be found within two standard deviations or, put another way, that we can say with 95% certainty that the activity will be completed withing the two sigma range.
- At three sigma there is a 99,7% probability.
Lets apply this to Activity A:
- A 68% probability of completing the activity between 6.3 and 9.7 days.
- A 95% probability of completing the activity between 4.6 and 11.3 days.
- A 99.7% probability of completing the activity between 3.0 and 13.0 days.
The same formulas can be used to calculate the one, two and three sigma figures for all the activities:
How can PERT help us at project level?
- There is a 68% probability that the project will be completed between 53.8 and 66.8 days.
- There is a 95% probability that the project will be completed between 47.3 and 73.3 days.
- There is a 99.7% probability that the project will be completed between 40.8 and 79.8 days.
In practice these percentages can be used to indicate to the sponsor that, due to the uncertainty regarding the estimates, there is a:
- 50% probability that the project will be completed within 60 days.
- 68% probability that the project will be completed within 67 days.
- 95% probability that the project will be completed within 73 days.
- 99.7% probability that the project will be completed within 80 days.
Enjoyed this article? Leave a comment below; or share it with your friends – Tweet, Like, Follow, or Pin it with the share buttons in the side bar
RSS Feed