PROJECT MANAGEMENT TRAINING AFRICA
Home
About
Who is PMTA?
Trainer
>
Dave Fourie
Clients
Courses
PMP/CAPM exam preparation
CEPM - Construction and Engineering Project Management
Best Practice Project Management
MS Project 2010, 2013, 2016 and 2019
Quality management on Projects
Risks management on Projects
Downloads
Publications
Contact
Exercise 1
Question
How many days float does activity E have?
a) 6 days
b) 10 days
c) 0 days
d) 9 days
Solution